Work is continuing on phase 2

Airport news

Share on Facebook Share on Twitter Share on Google+

The closure phase of the airport is coming to an end after 12 days and 12 nights. Over 30 people were at work each day and a team of 5 people every night. On the last two days, almost 100 people were working on the site.

The next phase will begin on Sunday 30 April at 7 a.m. local time. Planes will be able to fly along the new flight paths Alpha, Bravo and Charlie. Special attention is required, since building work is continuing in the rest of the airport.

Building work schedule available in: Practical information / publications